Town page
WatchdogResale CO checklist

Saddle Brook Township

Bergen County, New Jersey · Checked October 4, 2026

Certificate of Occupancy Required

Resale Certificate · Township of Saddle Brook Building Department (Construction Official / Fire Official inspection; Property Maintenance Officer checks the exterior)

  • Proof of payment of the $200 water meter fee (Water Department)
  • Payment of the Resale Certificate fee, a completed application and an approved inspection
  • Ten-year sealed battery smoke alarms on each level and outside each sleeping area; hardwired alarms (installed after 1995) in bedrooms, near bedrooms and on each story, not replaced with battery units
  • Carbon monoxide detector within 10 feet of all sleeping areas
  • Low voltage fire alarm systems tested by a licensed electrician or fire alarm contractor, with the report submitted before the inspection
  • Secondary power source warning label (generators, solar, battery storage) within 18 inches of the main panel and meter
  • Property Maintenance Officer inspects the sidewalk and the whole exterior
  • Open permits are checked on the application
Resale Certificate fee$125
New application if the closing does not happen within 60 days$100
Water meter fee on the sale of any home (paid to the Water Department; proof needed)$200

Smoke and CO alarm certificate Required

  • Ten-year sealed battery smoke alarms on each level and outside each separate sleeping area; hardwired alarms (post-1995) kept and not replaced with battery units
  • Carbon monoxide detector within 10 feet of all sleeping areas
  • Low voltage fire alarm systems tested with a report
  • Secondary power source warning label for generators, solar or battery storage
  • The August 2025 form no longer lists a fire extinguisher

Saddle Brook Township Fire Prevention Bureau / Fire Official, inspected as part of the Building Department Resale Certificate

Smoke and carbon monoxide detector certificate, per inspection (Code Section 93-10F); reinspections cost the same$50